ISRO and NASA are collaborating to conduct a low Earth Orbit observatory mission called NASA-ISRO Synthetic Aperture Radar (NISAR) mission. The project aims to study the Earth’s ecosystems, dynamic surfaces, and ice masses. Additionally, the NISAR mission aims to have a thorough understanding of natural disasters, sea levels, and groundwater levels. (NASA/JPL)
1/5 ISRO and NASA are collaborating to conduct a low Earth Orbit observatory mission called NASA-ISRO Synthetic Aperture Radar (NISAR) mission. The project aims to study the Earth’s ecosystems, dynamic surfaces, and ice masses. Additionally, the NISAR mission aims to have a thorough understanding of natural disasters, sea levels, and groundwater levels. (NASA/JPL)
The NISAR mission is expected to be conducted in three phases. As of now, ISRO is conducting different series of tests for the official launch of the mission. Recently, ISRO successfully conducted a 21-day test during which the satellite was kept under a thermal vacuum chamber. (NASA/JPL)
2/5 The NISAR mission is expected to be conducted in three phases. As of now, ISRO is conducting different series of tests for the official launch of the mission. Recently, ISRO successfully conducted a 21-day test during which the satellite was kept under a thermal vacuum chamber. (NASA/JPL)
NISAR mission launch phase: The mission will be launched from Satish Dhawan Space Centre(SDSC) SHAR, Sriharikota with ISRO’s GSLV expendable launch vehicle. After the launch and post-separation, the mission launch phase will be concluded with solar array deployment along with placing the observatory in an Earth-pointed attitude and enabling two-way communication with the ground. (Pixabay)
3/5 NISAR mission launch phase: The mission will be launched from Satish Dhawan Space Centre(SDSC) SHAR, Sriharikota with ISRO’s GSLV expendable launch vehicle. After the launch and post-separation, the mission launch phase will be concluded with solar array deployment along with placing the observatory in an Earth-pointed attitude and enabling two-way communication with the ground. (Pixabay)
NISAR mission commissioning phase: The first 90 days of this ISRO-NASA mission will conduct in-orbit checkout (IOC) which will prepare the observatory for further science operations. Commissioning will also be done in subsequent phases: initial checkout, spacecraft checkout and instrument checkout. These phases will test each instrument and payload independently. (NASA/JPL)
4/5 NISAR mission commissioning phase: The first 90 days of this ISRO-NASA mission will conduct in-orbit checkout (IOC) which will prepare the observatory for further science operations. Commissioning will also be done in subsequent phases: initial checkout, spacecraft checkout and instrument checkout. These phases will test each instrument and payload independently. (NASA/JPL)
NISAR mission science operation phase: The science operation phase will be conducted during the end of the commissioning phase and it will be conducted for 3 years. During this phase, several scheduled manoeuvres will be conducted to maintain the science orbit and to avoid any conflict which could affect the observations. (Pixabay)
5/5 NISAR mission science operation phase: The science operation phase will be conducted during the end of the commissioning phase and it will be conducted for 3 years. During this phase, several scheduled manoeuvres will be conducted to maintain the science orbit and to avoid any conflict which could affect the observations. (Pixabay)